In a recent networking event that I hosted on Effective
Agile Transformation, a question came up from interested attendees on whether a
Project Management Office or Program Management Office (PMO) should have
different metrics to measure projects. An example of a metric that was tossed
around was that projects in a traditional waterfall approach may use schedule
variance whereas agile projects may measure velocity.
I believe these questions are rooted in traditional thinking
where people look up to Agile as a radical way of doing projects differently
only to arrive at the same results. Stacey’s diagram that Agile principles
promote call out that not all projects will benefit from applying
agile principles of iterative and incremental delivery. So, all types of
projects should be evaluated based on value generation. Any type of key
performance indicator basically evaluates this value generation as evidenced by
Michael Porter’s value chain theory where project management is an indispensable support management activity.
First, PMO (sometimes called Value Management Office, Value Delivery Office, Centers of Excellence), is a portfolio function (which means there is no end date, and any project/program may or may not be related). The goal of the PMO is a governance function rather than management function. The PMO should continuously review seismic changes in the market and its impact on the organization (external influences) and plan to build capability and capacity. So, PMO functions are not just metrics driven. In my opinion, PMO is responsible for the following so that the organization's strategy and goals are supported sometimes by allowing to take on projects never taken by the organization before laying the foundations of profit center.
- 3C: Capability, Capacity, Change Planning (e.g., EEF/OPA support)
- 3R: Resources, Risks, Reporting
- Knowledge Management is supported by focusing on both 3Cs and 3Rs through ongoing training and evaluation.
As some organizations are in the emerging stages with five different levels (like supportive, controlling, directive, mature, and optimizing), it is possible that the PMO focus takes on some levels of measures of performance and metrics to monitor these measures. From that angle, let us explore profit center thoughts from a measure's perspective.
For instance, let us consider “Time to market.” This metric
measures the elapsed time from the onset of the project to its delivery. Measured
from the start date to the end date in the baseline may go for, say 8 weeks.
Now, an experienced project manager may use the “80-hour” productivity rule to
mark a milestone introducing checkpoints for incremental value delivery. This
milestone may be a requirement freeze, delivery of a certain development,
receipt of assets from a client, procurement of a vendor contract, etc. This 80-hour commitment is already making a
project manager think agile in a project that need not lend itself for agile
implementation. Unlike an agile project, this 80-hour duration need not be
equated to a certain number of story points to establish a team velocity.
Therefore, while every PMO needs to be formed based on
business needs and not all metrics may be equally extended to all PMOs, I
believe and challenge all business driven PMOs to think and act like Profit
Centers instead of cost centers while measuring value generation. This value generation
underscores project managers to become skilled at proactively managing the
projects by becoming subject matter experts in the domain skills relevant to
the project, master organizational skills to mitigate risks, learn negotiation
skills to control the project scope but allowing changes, and understand empowerment
skills in energizing and motivating the team.
As an example, let us take the “Time to market.” Let us say,
if two similar projects that focus on developing a website are developed by two
different project managers. Now, if on a consistent basis one project manager
can deliver projects of similar complexity in 6 weeks while the other project
manager takes 8 weeks to deliver, then,
the skilled project manager has shown the organization that the cost savings
for 2 weeks on a consistent basis from the agreed project baseline duration of
8 weeks. If PMOs operate as profit centers, then, the PMO can look for
increasing the skills of the PM in project management areas to think and be
agile.
What are your thoughts?