Earlier in the blog, we had discussed an overview of
RACI. It is a great tool in every project and is an important tool in the Portfolio,
Product, Program, Project, and Process Management Office (I call this P5MO). Too often, however, not knowing how to use this tool is like having a wrench
used when a screwdriver is needed, leading to the tool’s failure. So, let me
address a few key observations based on my experience working with people that
apply the tool incorrectly. I would like to come up with a list of 8 key findings. These
are listed in no specific order as follows.
Number
|
Challenge
|
Possible Problems
|
1
|
Too many R’s
|
This is the person that does the work! If there are too many people involved, then the task is adequately defined leaving ambiguity in the task.
As a result, many people are required to perform.
Now, agile teams may think the work effort is shared in a
self-organized team addressing central dependency of failure. This is quite
understandable, but then, there should be fewer R’s. Per design, an agile
team should not be more than 7 in total including the scrum master and
product owner. So, if you see 3+ Rs
for a task, then, trouble is brewing!
|
2
|
Too many A’s
|
This is the person that is answerable to the management and resolves impediments for the team when there is confusion! Too many A’s is an
indication of chaotic control. It is like everybody wants to be engineering
the solution, but nobody is leading.
This could also be an indication of lack of knowledge in the groups
expected to be held accountable that holds the “R” members accountable. Agile
addresses this concisely by having the product owner ultimately accountable
for prioritizing the user stories, decision making in the iteration backlogs,
and in grooming the backlog.
|
3
|
No R’s
|
This is the opposite extreme of an earlier problem and is equally
severe. There is no one to do the work! One may associate this with the “anybody
could have done the job, but nobody did the job” because no one was held to
it.
This is a severe issue with the project management particularly. It
is possible to have this issue when a task can’t be associated with anyone
because the organization has not provided a structure for it. Then, this is
something that the project manager must identify in the risk register and
follow through to get a closure.
|
4
|
No A’s
|
This is the opposite extreme of an earlier problem with much severe
risk exposure. There is no accountability for any work done, leaving anything being acceptable leaving the customers feel the pain.
This issue presents itself in the internal team members having multitude
of meetings to figure our solutions leading to lack of productivity. When this
happens, there is a “Skill/task” alignment mismatch potentially.
In my humble opinion, this should not be associated with people’s morale
due to trust erosion or due to organizational challenges. If any such thing
existed, then, the organization must step up to ensure that the
accountability is properly addressed.
No customer (internal or external) should be waiting on decisions or
success/failure requirements of a task as this is fundamentally against the
lean principle.
|
5
|
Empty spaces
|
If this observation exists, then, the RACI is incomplete. If this
really happens to be the case, then, the project manager or the person listed
as “responsible” and the person listed as held “accountable”
should be raising their voice. If a comparable entry in the risk register is
absent so that this can be resolved, this is like an accident waiting to happen.
|
6
|
Mixed letters
|
Occasionally, it is possible to have an accountable function along
with responsible function. For instance, an internally facing project manager is also accountable to talk with the client. However, such occurrences should be
very minimal.
It is however not acceptable to see such occurrences in some areas
for tasks like “development and QA” or “QA and deployment” because this would
defeat the purpose of role-assignment matrix (RAM). If this exists because of
resource constraints, there should be adequate process control. Combined with
resource constraints and process gaps, this is a potential for “Quality
failure by design” and is also, I believe, a means to “Escaped defects.”
I also think that a “R” and “A” are both “C” and “I” to
a large extent. But, listing “CA” or “IR” is an issue because then it raises
the question of whether the person is first consulting and then accountable?
RACI should avoid such ambiguities and should be a birthplace with mixed
responsibilities.
|
7
|
Lots of C’s
|
If too many C’s exist, then, I believe 3 potential problems may
exist.
The first one is that there is
a skill/task alignment with people listed as responsible/accountable leading
to decision by committee. No ownership exists and people are simply trying to
cover their trails.
The second one is that the culture or project itself may
be so risky that several stakeholders may want to weigh in and potentially
slowing down decision making and unnecessary escalations (needless to
reinforce here the number of communication channels that exponentially
increase here).
The third one is that the underlying processes and tools are
neither understood nor clear requiring more conscious checking of “Am I doing
it right?”
It is critical for an organization to review the RACI in such cases
and address these concerns with an iron hand.
|
8
|
Lots of I’s
|
This issue may not be as severe as Lots of C’s but may be attenuated
in some departments. However, it must be acknowledged that “being informed”
is to be addressed in the communication plan of a project. At times, the
person listed as “I” may have to promote to “C” so that no project gets
derailed at times of scope creep, technical debt management, quality issues,
customer concerns, etc. It is critical to note that the project consciously address
the “I” members balancing the unnecessary slowdown but mitigate any derailment to a
project by misinforming a stakeholder.
|
As you can see, developing RACI correctly is both an art and
science. It is an important tool that comes to the project’s aid and should be
developed with the utmost care it deserves for it to later benefit everyone
that is part of the RACI chart. Wouldn’t you agree?
No comments:
Post a Comment